There is a need for clear rules stating data centres would have commissioning timelines accelerated in return for incorporating storage, but cybersecurity issues are a big concern, according to panel convened by Tamarindo in partnership with Troutman Pepper Locke
Widespread deployment of battery energy storage systems by data centres will depend on stronger incentives, which could include accelerated connection timelines in exchange for integrating storage. Without such signals, developers and grid operators will lack the motivation to address the issue. These were among the conclusions of a Tamarindo roundtable – held in partnership with Troutman Pepper Locke – that sought to identify data centre opportunities for the battery storage sector in the US and Europe.
In order for a compelling business case to be made for developing battery storage facilities in conjunction with a data centre, there needs to be clear rules that state the data centre would have its commissioning timeline accelerated in return for incorporating storage, Vaughn Morrison, partner at Troutman Pepper Locke said. He added that such rules “exist in certain sub-markets within the US, but not all”. Morrison continued: “Some of the independent service operators have tariff rules that allow for applying for non-firm service that takes into account the proposed behind-the-meter resources, and, in those markets, it can be an effective strategy.”
Lost opportunity
Elsewhere, grid operators are becoming more aware of the potential for offering conditional grid connection agreements to data centre operators, fellow panellist Erik Strømsø, CEO and co-founder of BW ESS, said. He added that this would create a business case for data centres to develop battery storage assets. “If it [developing a battery asset] brings your data centre forward by five years, that’s the difference between having a viable data centre and having nothing,” he said. Strømsø added that it is “a lost opportunity to give a data centre a fixed connection agreement, when you could just tell them across the board that we will not give data centres a connection that includes loads during peak load hours.” Such a rule would incentivise data centres to build batteries, he argued.
Meanwhile, Sabelo Siyakatshana, director at SMBC Group, said regulation would have a role to play in incentivising data centres to develop battery storage assets. “If you can do it without [BESS], it’s probably the preferred route – bringing in battery storage brings in a lot of complexities into the deal in terms of rights, and you think about how hyperscalers prefer to set up their sites, they’ve got multiple redundancies, the dispatch requirements as well are quite strict, expecting 99.9% uptime,” he explained. “So combining a hyperscale data centre project, whether it’s AI or cloud, with another element which requires further negotiation of rights, is quite complicated, and for a lender, it’s even more complicated because you’ve got to deal with the maintenance side of the battery business and understanding the creditworthiness of those counterparties and their incentives, so it really complicates the projects a lot more.”
Cybersecurity is a big worry
A key challenge for the data centre industry when selecting battery storage suppliers will be to ascertain the expected longevity of the suppliers they choose, Paweł Kordala, head of investment office and deputy CIO at R.Power Renewables said. “They [data centres] have to take a view, and increasingly so in Europe, on Chinese battery producers and they have to be sure that these battery producers will have their service teams for 20 years after they sell the battery,” he added. “These are different kinds of risks that they have to face.”
Nikita Patil, strategy manager UK & Ireland at Fluence acknowledged that, with regard to battery producers from “countries of concern”, cybersecurity was the biggest worry not only for data centres but also for a lot of countries, which are “pushing for BESS to meet NIS2 [the EU directive on cybersecurity] requirements to make sure there is no such risk”. Patil added that the UK’s NCSC [National Cyber Security Centre] is looking at BESS-related cybersecurity risks. She continued: “There are quite a few examples of BESS being used as transmission assets that perform critical grid-stabilisation activities – such as the grid boosters in Germany – and there are a lot of ways to make sure BESS is safeguarded and there are controls in place to ensure cybersecurity is considered.” Patil also said that a change in mindset on the part of data centre developers might be useful in that there are advantages in adding battery storage to sites such as “releasing hosting capacity at the [grid] connection”.