NORD/LB and ECO STOR announce Foerderstedt BESS project, the “largest ever financed” in Germany, despite the nation’s storage market facing a raft of challenges including declining revenues, huge grid connection queues and uncertainty surrounding the regulatory framework
It’s been a big week in the German battery energy storage system (BESS) market with NORD/LB, together with Banco Santander and ECO STOR, announcing a financing package for the 300MW/718MWh Foerderstedt BESS site in Germany. The project, which NORD/LB described as the largest ever financed in the country, is expected to go live in 2027.
Key to the success of the financing was the recently announced long-term flexibility tolling agreement with Next Kraftwerke, a virtual power plant operator. NORD/LB said that the tolling agreement would provide a long-term commercial framework for the project and enable the battery to be “optimised across multiple energy and balancing markets”. Crucially, the structure combined revenue certainty with operational flexibility, which was key to supporting the project’s financing.
ECO STOR, in particular, views the financing as a major breakthrough, especially given the significant challenges facing the German BESS market. So what exactly are these challenges?
It’s been reported that achievable BESS revenues declined by 19 per cent in the year to February 2026. In addition, it has been forecast that German BESS revenues could drop by around 25 per cent in 2027 and could be around 50 per cent less than current levels in 2029 (see chart below).

German BESS Revenue Outlook 2026–2040 (Source: https://de-bess-outlook.streamlit.app/)
The German market is experiencing upheaval from a regulatory perspective. For example, the legal classification of battery storage is unclear, specifically in relation to generation, grid consumption and grid operation. Also, it is argued regulations regarding grid fees and grid connection contributions impact on the development of viable business models – for example, the German Federal Court of Justice ruled that levying grid connection fees on purely grid-connected battery storage systems was warranted. However, the Court also granted grid operators discretionary power to decide whether to offer incentives for the development of storage facilities when levying grid connection fees.
A large amount of grid connection requests are being filed in Germany, with the Federal Network Agency reporting that grid operators received nearly 10,000 connection requests for BESS at the medium-voltage level in 2024, totalling 400GW and 661GWh. Only 3,800 requests were actually approved, amounting to 400GW and 661GWh. The issue is that the approval process operates on a ‘first come, first served’ basis that makes little distinction between “technically feasible projects and speculative applications”, according to the professional services firm Rödl. The result is an unpredictable queue that slows down the approval process for all involved and makes project planning uncertain.
Though this is an issue that affects all BESS markets, and not just Germany, ageing and cell imbalance significantly impact the performance, safety, and lifespan of batteries. Battery asset owners and financiers face the challenge of understanding calendar aging and cycle aging in order to develop accurate predictive models for battery lifespan estimation. Cell imbalance arises from manufacturing inconsistencies, operational stresses, and aging variations among cells in a battery pack. Imbalanced cells lead to uneven charging and discharging, reduced pack efficiency, and safety risks such as thermal runaway.
As Jörn Rohland, CFO at ECO STOR, said the Foerderstedt BESS financing is a “remarkable achievement at a time when regulatory frameworks, market structures and revenue models continue to evolve”. Despite the numerous challenges facing the German market, investors see enormous potential for the wide-scale build out of BESS in the country. This confidence was exemplified earlier this year when it was announced that TotalEnergies had signed an agreement with Allianz Global Investors for the sale of a 50 per cent stake in a portfolio of 11 battery storage projects with a total capacity of 789 MW/1628 MWh. As a result of the agreement, the partners said they would deliver an investment of €500 million in “critical energy infrastructure for Germany”.
The financing of the Foerderstedt project represents a key milestone for Germany’s rapidly evolving BESS sector as it proves large-scale storage assets can attract major financial backing despite mounting market and regulatory challenges. Yes, declining revenues, grid connection queues, regulatory uncertainty and battery performance-related risks continue to create headwinds, but innovative commercial structures – such as long-term tolling agreements – will continue to bridge the gap between investor expectations and market realities. If Germany can successfully implement market reforms, the country’s BESS industry will be on a sound footing for the decades to come.
As capital continues to flow into German energy storage, the sector’s long-term growth prospects remain strong. The key question now is whether policy and market reforms can keep pace.