Top UK power-to-X executives told Tamarindo’s Leadership Council that delays with Hydrogen Allocation Round 2 are destroying project value, but said the industry could help unblock the process by offer a clearer ‘quid pro quo’ of how they would solve key industrial challenges.
UK green hydrogen developers must offer politicians a compelling ‘quid pro quo’ to remove power-to-X development delays.
That was a key point to take away from the the 15th meeting of Tamarindo’s Power-to-X Leadership Council group of senior executives in the green hydrogen and power-to-X industry, which was held in London on 9th June. This private invitation-only discussion enabled attendees to reflect on the biggest challenges facing developers and investors in this emerging sector, with a particular focus this time on the UK market.
Panellists discussed the damage being done to the sector due to a lack of clarity from the UK Government about when it would award final contracts under the second Hydrogen Allocation Round (HAR) process. The UK shortlisted 27 projects totalling 765MW in England, Scotland and Wales for support in April 2025. Projects are going through a due diligence and cost assurance process managed by the Department for Energy Security and Net Zero, and this process is due to conclude this year. At present, developers have no visibility about when that will happen.
Attendees said this lack of clarity is not just an inconvenience, but is undermining the value of projects.
One big challenge here is from data centres, which are growing rapidly to meet booming demand for digital services based on artificial intelligence and represent competition for investment. Delays with final HAR2 contracts mean banks are finding it tougher to make a case to allocate resources to hydrogen projects, which are often smaller deals than data centres and slower to come to fruition.
In addition, data centres are hungry for electricity and could use power produced by generation sources that would be linked to hydrogen production plants. However, this could be beneficial for green hydrogen developers if this source of offtake deals bridges the gap between building renewables generation now and hydrogen plants coming online.
But there is a major risk that developers stop waiting and decide to focus their efforts, time and money elsewhere if the UK Government continues to delay in key areas. Attendees at the Leadership Council meeting said they need clarity about the conclusion of HAR2; about design parameters for HAR3, where the industry expects a meaningful downgrade from ambitions set back in 2021; and about updates to the UK Hydrogen Strategy, which are due this year.
Difficulties in these areas are driving a change in the market, with attendees highlighting that the UK is splitting into two tracks.
One track is the large HAR projects dependent on subsidies, but the delays to the scheme mean they are stalled, expensive to maintain, and subject to competition for electricity. The other track is for small commercially viable hydrogen projects with a closed ecosystem and built-in demand for the hydrogen they produce. Projects in that second group are happening because they are less exposed to policy delays, but the fact they are small means that they are not a substitute for larger HAR projects if the UK wants to grow hydrogen production fast.
But this is not just a call for the UK Government to act. There is an onus on industry to adapt too.
Quid pro quo for policymakers
Attendees discussed how power-to-X companies could change how they engage with politicians, with some executives highlighting that too much attention is on requesting subsidy support and clarity on regimes such as HAR. This puts hydrogen developers in the position of asking policymakers for money and information, rather than offering a quid pro quo to solve power-to-X problems. Companies could, for example, make more progress if they can articulate a credible commitment to cost reduction in exchange for regulatory certainty, long framework agreements, and targeted interventions on power pricing.
The way the UK battery sector has engaged with the National Energy System Operator to show the benefits of batteries to balance the grid and provide frequency response services was given as a case study, because this shows that battery companies are seeking to match their services with the priorities of policymakers. Creating value and solving structural issues in the UK energy system is more compelling than primarily requesting clarity about support.
The Power-to-X Leadership Council also discussed how a more nuanced position on Carbon Capture, Utilisation and Storage could support sustainable fuel production in the UK. At present, the policy framework in the UK incentivises carbon sequestration rather than carbon utilisation, but biogenic carbon dioxide could be routed to sustainable fuel production rather than being stored under the North Sea. This could strengthen the economics of UK power-to-X.
If the industry identifies more of these opportunities and makes a credible commitment to reducing costs as power-to-X deployment increases then this could help win support and unblock the current logjams. The industry has not yet reached a level of deployment where it can demonstrate that trajectory, but companies could do more to show credible plans for how they would seek to achieve this.
If the UK power-to-X industry can speak with a united voice, backed by a clear data-driven case, then this would be more effective than what is happening now.
This does not guarantee the UK Government will respond, but it could help to break a longstanding impasse.