RENEWABLE ENERGY CLAIMS CONFERENCE 2026
Delay in Start Up (DSU) claims are among the most challenging types of claims to handle in the renewable energy sector. Steven Horne, Director and Advisor at Oak Advisory & Resolution, recently spoke to us about the factors that make DSU claims more complex than they could be and the ways in which the industry is adapting to more proactively manage these scenarios.
Along with Paul Lowrie, Partner at Clyde&Co, Steve will be taking to the stage at the inaugural Renewable Energy Claims Conference (RECC) in October as they deliver a session on ‘making sense of complex DSU claims’, where they dissect technology-specific case studies from onshore and offshore projects.
DSU is traditionally seen as one of the most complex areas of insurance, to what extent is it impacting the renewables market?
DSU claims are complex enough when a project has just one, or a few, operating units, which has traditionally been the case for DSU claims. The real question, though, is how the renewables market is impacting DSU. The typical renewables project has multiple operating units and can reach commercial operation before final energisation, and, where some units may experience catastrophic damage, it can struggle to sit within the traditional DSU framework.
Taking offshore wind as an example, some projects consist of more than 100 wind turbine generators (WTGs) and the process of bringing WTGs online can last months or even years. Where policies contain only a single Scheduled Commercial Operation Date (SCOD), we have seen significant Erection All Risks (EAR) incidents fail to trigger a DSU. Likewise, we have seen Increased Cost of Working (ICOW) claims fail when economic tests are measured against energisation of the final operating unit. DSU must now adapt to ensure that such projects have adequate cover at a level of risk acceptable to underwriters.
What other scenarios add complexity to DSU in the renewables market?
Seasonal weather fluctuation presents further challenges for renewables projects that experience DSU. We have seen cases of DSU outcomes that are disproportionate to the immediate impact of an insured event – that is, a relatively minor insured incident leading to an extended delay, which compounds financial loss. This can occur during winter shutdowns, both onshore and offshore, or during an event that creates subsequent commissioning difficulties by placing a project in a more challenging season. We have seen this in run-of-river hydropower and solar farms.
Equally, it is possible for an insurable event to place a project back into a favourable commissioning season when other, non-incident related, delays also impact a project. So, there is an element of luck involved, but this is not something the industry can confidently rely on.
What are the common misconceptions about DSU in the market?
DSU claims do not, at their core, need to be complex – that’s the point that Paul and I would like to make at RECC. Simplistically, DSU is just the difference between two dates: the SCOD (or ‘but for…’ commercial operation date) and the actual commercial operation date.
Complexity arises because the SCOD is inherently a hypothetical date. The earlier an event occurs in the project timeline, the harder it is to demonstrate a direct, causal critical delay. This is then often compounded by DSU claims being placed at the bottom of the ‘to do’ list. It is not uncommon to review events that have occurred years in the past, by which time establishing facts, or filling gaps in project records, is more difficult.
The simplest, and best, DSU outcomes happen when all the relevant parties establish communication lines quickly in the aftermath of an event to understand and gather all the information that is needed to support a claim.
How is the market adapting to complex DSU experiences and managing better outcomes?
The market is doing a better job now at communicating. Something we are seeing much more of is discussion between stakeholders outside of live claims, which speaks to a more proactive stance on DSU. Creating steering groups and trying to bring more clarity to contentious issues in advance of them occurring is a great development for the market and we view these initiatives as vital to improving DSU claims experiences.
What is the one key message you want the audience at the Renewable Energy Claims Conference to walk away with to make their next DSU claim smoother?
Meaningfully engage with all stakeholders as early as you can following a potentially critical incident. The moment immediately after such an incident is pivotal because it carries the greatest potential to implement mitigation measures with buy-in from all parties and to fully understand the circumstances and challenges that the project faces when it comes to reinstating the damage that has occurred. The most effective way to achieve a smoother DSU claim is to give DSU its due importance on your list of priorities.
What are you most looking forward to getting out of the conference?
Every good conference helps to move the conversation along a little further to help resolve common issues in a vitally important industry. That’s my aim for a notoriously difficult claims issue like DSU. Paul and I may be talking about how to make sense of complex DSU claims right now, but, hopefully, more sessions like this can put us in a position to talk about how DSU claims have become simpler for the industry to handle in years to come. I’m excited to see where this conversation takes us next!